    Planning Speedrun

    Give Atlasly a UK location. It reads the site against official planning, heritage, ecology and ground datasets, works out what would genuinely move the project forward, then runs the next fortnight in front of you — checking every weather-dependent activity against a Google DeepMind WeatherNext 3 ensemble and adapting when a day will not work.

    Try

    Real constraints, not a summary

    The run reads the same official datasets Atlas AI uses — Environment Agency flood zones, planning.data.gov.uk conservation areas and Article 4 directions, Historic England listings, Natural England designations, EA historic landfill and BGS ground screening. Where a dataset has no coverage, the run says so rather than reporting an all-clear.

    Weather that changes the plan

    Every field activity carries defensible limits — a UAV flight stands down above 9.5 m/s, a bat emergence survey needs 10 °C and light wind at dusk, a rig needs ground that three days of rain has not made impassable. WeatherNext 3 ensemble percentiles decide whether a day clears those limits, and how confidently.

    Adaptive, not a Gantt chart

    When the next activity cannot happen, Atlasly says which limit stopped it, books it into the next window the ensemble supports, and spends the day on the work that can move. What you get at the end is a programme, with the blockers still named.

    What this tool does not do

    • It does not carry out surveys. A scheduled activity is a window Atlasly believes is workable, not work that has happened.
    • It does not exercise professional judgement, and it does not replace an ecologist, arboriculturalist, geotechnical engineer or planning consultant.
    • It does not submit anything or predict a planning decision. Where the programme reaches an authority, Atlasly prepares the enquiry — the authority decides.
    • WeatherNext 3 is an experimental AI forecast system and is not an official warning service. Official UK severe weather warnings come from the Met Office, shown separately and never merged into the forecast.
    • Progress is reported as counts of what was prepared, scheduled or left open. There is no completion percentage, because there is no honest denominator for one.